01Why it matters
Everything about a septic system, its type, its size, where it can sit, and what it costs, is determined by two things: what the soil will accept and how many bedrooms the house has.
You find out the first by digging test pits and reading the soil profile. There is no substitute and no way to estimate it from a map. Two neighbouring lots can produce completely different answers.
That is more true in Whatcom County than in most places, because the ground varies enormously across short distances and because winter groundwater is a genuine design constraint rather than a footnote. A design that assumes summer conditions produces a system that struggles every January for the rest of its life.
Getting the design right is also what makes the permit straightforward. Most permit delays are not the county being slow, they are applications going back and forth because something in the submission did not stand up.
02Scope
Test pits, soil profile logging, groundwater assessment, and establishing the usable area of the lot once wells, water, buildings, slopes and property lines are accounted for.
The system type and layout that the soil and the bedroom count require, whether that is conventional gravity, pressure distribution, a sand filter or a mound.
The application, drawings and supporting documentation, prepared, submitted and followed through review with the county.
03Included
Dug, logged and recorded properly. This is the foundation of the entire design and it is the step people most often want to skip.
What the water table does here in winter, not just what it is doing on the day we visit. In this county that distinction changes designs.
Where a system can legally and practically go once wells, surface water, buildings, drives and boundaries are accounted for. On tight lots this occasionally changes where a house can be built.
A complete package prepared to what the county expects, submitted, and followed through review including responding to comments.

04How it runs
Most routine visits follow this exact sequence. If yours will not, we say so when you book rather than on the day.
New build or replacement, bedroom count, where the house and drive will go, and where the well is or will be.
Test pits dug and logged, soil profile read, groundwater assessed, usable area established.
System type and layout matched to what the soil will accept and what the house requires.
What the design means practically: where the field lands in the yard, what you cannot build or park on afterwards, and what it will cost to install.
Package prepared and submitted, comments responded to, approval followed through.
Approved design goes to installation, either with us or with whoever you choose. The design is yours either way.
05Why us
We design for February. A soil evaluation carried out in a dry spell can produce a design that is technically defensible and practically optimistic. Accounting for what a site does in the wet months is the single most valuable judgement call in this county, and it is the one most often skipped.
We design and install, which means the design has to survive contact with reality. A designer who never installs can produce something that is awkward or expensive to build. Knowing we may be the ones digging it keeps the design honest.
We are straight about timelines. County review takes what it takes. We will tell you the realistic range rather than the optimistic one, because planning a build around an optimistic permit date is how projects go wrong.
And the design belongs to you. If you take it to another installer, that is entirely reasonable and it happens. We would rather do good design work than lock people in.
Everything downstream depends on the soil. Start there.
06What customers say
Placeholder section.No reviews have been collected yet, and nothing here is invented to fill the space. Real customer reviews go in before this section publishes. Until then there is no star rating, no aggregate score and no review markup on this site.
07Questions
A soil and percolation assessment establishing how quickly the ground accepts water. It is the basis of the whole design, and on difficult ground the result can rule out a conventional system entirely.
Design, permitting and installation are all regulated. In practice this is not a homeowner project, and an unpermitted system creates serious problems at resale as well as legal and health exposure.
County review timelines vary with workload and with how complete the submission is. Most delays come from applications going back for missing or inadequate information rather than from the county being slow.
Tank and drain field sizing are both driven by bedroom count, which is used as the proxy for occupancy. The applicable figures come from code and are confirmed at design stage rather than from a rule of thumb.
Washington regulates onsite sewage systems at state level and counties administer their own programmes on top. Whatcom County runs its own onsite sewage programme, so the local requirements are what actually apply to your property. Our operation and maintenance guide covers the ongoing side.
That is common here and it is not the end of the project. Pressure distribution, sand filters and mound systems exist precisely for ground that will not take a gravity field. They cost more, and they work.
08Coverage
We work across Bellingham, Lynden, Ferndale, Blaine, Birch Bay, Everson, Nooksack, Sumas, Deming, Custer, Sudden Valley and Point Roberts.
09Related
Every other service we run, in case the job you have is not the one you came here for.
Routine and overdue pumping. Both chambers, lids dug out at no extra charge, and the tank inspected while it is open.
Property transfer and routine inspections, with a written report escrow and the county can both act on.
Baffles, lids, risers, pumps, alarms and blocked lines. We diagnose before anyone quotes a replacement.
Whether a saturated field can be recovered or genuinely needs replacing, and the evidence for the call.
New systems from site evaluation and soil testing through design, permit and final county inspection.
Full replacement when a system is finished, including decommissioning the old tank properly.
Backing up, alarm sounding, sewage surfacing. Same day response, priced before we start.
Finding a buried system on a property where nobody knows where anything is, and tracking down the as-built.
Lids brought to ground level so future service does not start with an hour of digging.
Effluent and grinder pumps, floats and alarm panels on pressurised, mound and sand filter systems.
10Book it
Tell us about the property, the bedroom count, and whether this is a new build or a replacement.